How to make a Gantt chart: a step-by-step guide

How to make a Gantt chart in 6 steps: list tasks, set durations, link dependencies, add milestones. With an example, free tool and Excel option.

To make a Gantt chart, list the tasks of your project, give each one a start date and a duration, and draw them as horizontal bars on a timeline. Then link the tasks that depend on each other and add milestones for the key dates. You can do it with a free online Gantt chart maker in a few minutes, or in a spreadsheet if you prefer.

What you need before you start

  • A goal: what the project delivers, in one sentence.
  • A deadline, or at least a target month.
  • The people involved, so each task can have an owner.

How to create a Gantt chart in 6 steps

  1. Set the goal and the end date. If the date is fixed, you will plan backwards from it.
  2. List the tasks. Break the work into tasks that take a few days to two weeks. Group them into three to six phases: planning, design, build, launch. Tasks longer than a month hide problems; split them.
  3. Estimate durations. Ask the person who will do the work. Add a little margin to tasks that depend on someone outside the team.
  4. Link dependencies. “Testing” cannot start before “Build” is finished. Draw that link: when one task slips, the tasks after it move too.
  5. Add milestones. A milestone has no duration: a sign-off, a delivery, a launch. Clients and managers read the milestones first.
  6. Share and update. A Gantt chart is useful only if it reflects reality. Update it after the weekly meeting and share a read-only link.
Build one in 2 minutesFree, no signup. Type a task, press Enter, drag the bar.
Make your Gantt chart

Example: a small website project

TaskDurationDepends on
Kickoff meeting1 day–
User research1 weekKickoff
Design2 weeksUser research
Build3 weeksDesign
Testing and fixes1 weekBuild
Launch (milestone)–Testing

On the chart, each row becomes a bar. Because every task waits for the one before, this is also the critical path: any delay pushes the launch. More layouts are in our Gantt chart examples.

Which tool to use

Online Gantt chart builderExcel or Google SheetsPowerPoint
Time to first chart2–5 min15–30 min10–20 min
Dependencies that moveYesNo (manual)No
Easy to shareRead-only linkFileSlide
Best forProjects you updateSimple, stable plansOne-off presentations

Step-by-step guides: how to make a Gantt chart in Excel, in Google Sheets and in PowerPoint. Or skip the setup with a ready-made Gantt chart template.

Common mistakes

  • Too much detail. 15 to 40 rows is plenty for most projects. Keep the to-do level on a Kanban board.
  • No dependencies. Without links, the chart looks right on day one and wrong by week two.
  • No owner. Every task needs a name next to it.
  • Never updated. Set a weekly slot to move the bars.

Questions

What is the easiest way to make a Gantt chart?

Use an online Gantt chart maker: type your tasks, drag the bars to set dates, and link dependencies. It takes a few minutes and needs no install.

Can I make a Gantt chart in Excel?

Yes, with a stacked bar chart or conditional formatting. It works for simple plans but dependencies don’t update on their own.

How many tasks should a Gantt chart have?

Most projects read well with 15 to 40 rows. Group tasks into phases and keep small to-dos elsewhere.

What is a gantt chart builder?

A tool that turns a list of tasks and dates into a Gantt chart, with bars you can drag and dependencies that move together.

Is there a free Gantt chart maker?

Yes. Ganttmint is free and works in the browser without an account.