Notion Gantt chart and Kanban board: timeline view, dependencies and limits

How to make a Gantt chart in Notion with the timeline view, link dependencies, build a Notion Kanban board, and where Notion stops as a project planner.

Notion has no view called Gantt, but its timeline view works like one. Any database can show its items as bars between a start and an end date, and you can link items with dependencies. The same database also opens as a board, Notion’s Kanban view. Here is how to set up both, and where Notion falls short for scheduling.

How to make a Gantt chart in Notion

  1. Create a database (type /database) with a Name, a Date property with an end date, a Status and an Assignee.
  2. Click + next to the view tabs and choose Timeline.
  3. In the view settings, set the timeline to use your date property, or separate start and end properties.
  4. Drag bars to move or resize tasks, and zoom from days to quarters.
  5. Turn on dependencies in the view settings, then drag from the edge of one bar to another to link them.

How to make a Kanban board in Notion

On the same database, add a Board view grouped by Status. Each status becomes a column; drag cards to move them. Add a Sprint or Priority property to filter the board, and keep the timeline view for dates. One database, two views, no duplicate tasks.

Where Notion stops

  • No critical path and no baseline to compare plan and reality.
  • Setup takes time: properties, views and filters are yours to build and maintain.
  • Sharing a plan with a client means publishing a page or inviting them to the workspace.
  • Exporting a Gantt chart as an image or a spreadsheet is not built in: you export the database as CSV.

Try it here:

Try a Gantt chart here firstFree, no account. Drag a bar: the linked tasks follow.
Make your Gantt chart

A faster option for a project timeline

If you need a Gantt chart today rather than a workspace, build it in Ganttmint: free, no account, dependencies that move, and a Kanban view of the same tasks. Already have the tasks in Notion? Export the database as CSV (⋯ menu, Export), keep the Name and date columns, and import the file from Ganttmint’s ⋯ menu.

Notion or Ganttmint?

Notion timelineGanttmint
Best forPlans inside a team wikiA project plan to share
SetupBuild the database and viewsNone
DependenciesYesYes
Critical pathNoYes
Kanban viewYes (board)Yes
ExportCSV, Markdown, PDF pagesPNG, PDF, Excel, CSV, read-only link

Comparing other tools? See Airtable, Asana and Trello. For the method, how to make a Gantt chart.

Questions

Does Notion have a Gantt chart?

Not by that name. The timeline view shows database items as bars on a calendar, with dependencies, which works as a simple Gantt chart.

Is the Notion timeline view free?

Yes, the timeline view is available on Notion’s free plan as well as paid plans.

How do I make a Kanban board in Notion?

Add a Board view to a database and group it by a Status property. Each status becomes a column.

Can Notion show dependencies?

Yes. Turn on dependencies in the timeline view settings, then drag from one bar to another.

Can I export a Notion timeline to a Gantt chart?

Export the database as CSV and import it into Ganttmint, which draws the Gantt chart and exports PNG, PDF or Excel.