Website project Gantt chart template
The typical flow of an agency or in-house team, from discovery workshops to go-live. Mobile and desktop designs run in parallel, development waits for sign-off, and QA gates the launch until it’s done.
12 tasks · 6 weeks
Edit it right here: rename, drag the bars, then go full screen to keep it.
How to use this template
- Open it in Ganttmint with the “Use this template” button. It starts this week, and everything stays in your browser.
- Make it yours: double-click a task to rename it, stretch a bar to change its duration. Linked tasks follow.
- Share it with a read-only link, or export it to Excel, PNG or PDF.
The Excel file
The file contains the task list and a Gantt sheet built with formulas: change a start date or a duration and the bars move on their own. Works in Excel, LibreOffice and Google Sheets.
Download for ExcelWebsite project
| Task | Duration (days) |
|---|---|
| Discovery | |
| Workshops and goals | 3 |
| SEO and content audit | 4 |
| Sitemap | 3 |
| Design | |
| Art direction | 4 |
| Desktop mockups | 7 |
| Mobile mockups | 6 |
| Designs approved | ◆ |
| Development | |
| Front-end build | 10 |
| Content migration | 6 |
| 301 redirects | 2 |
| Go-live | |
| QA testing | 4 |
| Site live | ◆ |